AS all are well aware, the GST law, insofar as it
concerns the Realty Sector, has been virtually re-written with effect from
1-4-2019 and that, the levy of GST at the lower rates without the benefit of
ITC is compulsory for projects which commence on or after 1-4-2019 and that, in
respect of 'ongoing projects', the Developer has the option to continue with the
old scheme wherein, ITC is allowed. Hence, the new scheme would, by and large,
boil down to the interpretation of the definitions of an 'ongoing project' and
'a project which commences on or after 1-4-2019'.
In terms of Notification No. 3/2019-CT(Rate) dated 29-3-2019, an 'ongoing project' is defined as under:
(xx) the term "ongoing
project" shall mean a project which meets all the following
conditions, namely-
(a) commencement
certificate in respect of the project, where required to be issued by the
competent authority, has been issued on or before 31st March, 2019, and it is
certified by any of the following that construction of the project has started
on or before 31st March, 2019:-
(i) an architect
registered with the Council of Architecture constituted under the Architects
Act, 1972 (20 of 1972); or
(ii) a chartered engineer
registered with the Institution of Engineers (India); or
(iii) a licensed surveyor of the respective local body of
the city or town or village or development or planning authority.
(b) where commencement
certificate in respect of the project, is not required to be issued by the
competent authority, it is certified by any of the authorities specified in
sub- clause (a) above that construction of the project has started on or before
the 31st March, 2019;
(c) completion
certificate has not been issued or first occupation of the project has not
taken place on or before the 31st March, 2019;
(d) apartments being constructed under the project have
been, partly or wholly, booked on or before the 31st March, 2019.
Explanation.- For the purpose of sub-
clause (a) and (b) above, construction of a project shall be considered to have
started on or before the 31st March, 2019, if the earthwork for site
preparation for the project has been completed and excavation for foundation
has started on or before the 31st March, 2019.
(xxi) "commencement
certificate" means the commencement certificate or the building permit
or the construction permit, by whatever name called issued by the competent
authority to allow or permit the promoter to begin development works on an
immovable property, as per the sanctioned plan;
(xxviii) "project
which commences on or after 1st April, 2019" shall mean a project
other than an ongoing project;
Now, look at the definition of a
project which commences on or after 1-4-2019, as per this Notification.
(xxviii) "project which commences on or after 1st
April, 2019" shall mean a project other than an ongoing project.
In terms of the above definitions,
any project which does not fulfil the definition of an 'ongoing project' would,
by default, get treated as a 'project which commences on or after 1-4-2019'
thereby forcing the Developer to go for the new scheme.
Can life be as simple as that?
Take the case of the requirement to
obtain a commencement certificate from the competent authority. This
requirement is virtually absent in many parts of the country and is prevalent
in some cities like Bengaluru wherein the commencement certificate is required
to be obtained from the Brugat Bengaluru Mahanagara Palike, popularly known as
BBMP. Any Developer would say that, he would need to go through a big and
laborious process to obtain the Commencement Certificate from the BBMP and in
many cases this certificate is obtained at the time when the construction is
almost over.
Many Developers have launched
residential projects in respect of which, significant construction activity has
already been completed and these projects could have been launched several
months ago and these Developers could have signed up many flat buyers. Prior to
1-4-2019, Developers were collecting GST @ 12% on the total value of the
project and life was fine. Since obtaining the commencement certificate was not
a pre-requisite, most of these Developers did not even bother to apply to the
BBMP for obtaining these commencement certificates.
Suddenly, on April Fools' Day this
year, all of these otherwise running projects without commencement
certificates, would cease to be treated as 'ongoing projects' and by default,
would get classified as projects commencing on or after 1-4-2019. Many
Developers have signed agreements with flat buyers on the basis of the
erstwhile GST regime, on the basis of the GST rate of 12% with ITC and they
suddenly find that, they are forced to shift to the new regime of charging GST
@ 5% without ITC, in respect of these otherwise running projects. Where is the
logic of treating these projects that have been running for several months, as
new projects commencing on or after 1-4-2019, only on the basis of the
technicality of these projects not having obtained the Commencement Certificate
on or before 31-3-2019? Does this requirement not discriminate a Developer who
is located in a place where the practice of obtaining a commencement
certificate from the competent authority as compared to a Developer who is
fortunate enough to be engaged in construction of a project in a city or town
where, there is no such requirement?
Taking this discussion forward… while
bringing such an important substantive requirement wherein, not obtaining the
commencement certificate prior to 1-4-2019 could result in the project being classified
as a new project commencing on or after 1-4-2019, shouldn't the Government have
given time to Developers to apply for and get these commencement certificates,
wherever it is necessary? Or, shouldn't the Government have issued Notification
No.3/2019-CTR well in advance, so that, Developers
could have applied for and obtained these commencement certificates. The
Government, sadly enough, seems to be oblivious of the ground realities related
to the obtaining of the commencement certificates and the simple fact that
these certificates are more of a procedural requirement and do not reflect the
actual quantum of work that could have been completed in a running project.
There is another issue that would
need discussion. As per the definition of an 'ongoing project', the Completion
Certificate, or the 'OC' as it is popularly referred to, should not have been
obtained on or before 31-3-2019. Here again, the Government seems not to have
appreciated the fact that, even after obtaining the OC, there could be
installments that would continue to fall due from the flat buyers and in many
cases, some amount of work such as painting, etc. could be done after the date
of the OC. With these projects wherein OC has been obtained before 1-4-2019,
would these projects be required to be classified as 'new projects commencing
on or after 1-4-2019', wherein, the Developer would necessarily need to charge
GST at the rate of 5%? Can anything be more unreasonable and illogical to treat
a project in respect of which OC has been obtained on or before 31-3-2019, as a
new project commencing on or after 1-4-2019?
One would request the government
machinery, who seem to blissfully unaware of the ground realities, while
drafting these draconian Notifications, to apply their minds to these scenarios
and come out with clarifications, before May 10, 2019 so that, the Developers
can accordingly exercise their options vis-à-vis their running projects.
Before parting…
A clarification to the effect that, running projects as of March 31,
2019 which fulfil the other requirements except for obtaining the commencement
certificate would still be treated as an 'ongoing project' would be of great
help to the Realty Sector. A further clarification to the effect that, the
balance installments falling due after the OC date, in respect of running
projects where OC has been obtained prior to 1-4-2019, shall continue to be
covered by the old scheme would also be hugely welcome. Since, the option to
shift to the new scheme for ongoing projects has to be exercised and the
requisite Form IV has to be filed on or before May 10, 2019, an urgent
clarification would hugely benefit this ailing Realty Sector.
No comments:
Post a Comment