CIT vs. Sambandam Udaykumar (Karnataka High Court)


The assessee sold shares for Rs. 4.18 crores and, within 12 months, invested Rs. 2.16 crores thereof to construct a house property and claimed exemption u/s 54F. However, as even after the expiry of 3 years of the date of transfer, the construction of the house was not complete and sale deed not executed, the AO & CIT (A) denied relief u/s 54F though the Tribunal granted it. On appeal by the department to the High Court, HELD dismissing the appeal: